Westmonte Renovation Update

If you've driven by Wesmonte Park lately, you may have noticed big changes. Here's the scoop on new developments:

  • The outdoor and therapeutic pools are constructed
  • All buildings are dried in, which consists of roofing, windows and doors
  • The foundation and grade of the parking lot has been established
  • Retaining walls on the east and northeast side of the park are complete
  • Building exteriors have been painted

The next work phase will focus on:

  • Bringing power to all buildings and testing mechanical equipment
  • Installing playground equipment
  • Adding curbs to the parking lot
  • Construction of the northwest and west retaining walls
  • Installing the stone veneer on buildings and columns

Last updated 1/24/2019